Facts
The plaintiff, Mr Bolton, agreed to install a combined central heating and hot water system in the defendant’s, Mr Mahadeva’s, home for a lump sum price of £560. Upon completion, the defendant complained that the system was defective. The defects were significant: the system failed to heat the house adequately, with the heat output being substantially lower than it should have been, and it produced fumes in the living room, making it uncomfortable and unsafe. The cost to remedy these defects was assessed by the trial judge to be £174.50. The defendant refused to pay any portion of the contract price. The plaintiff sued for the contract price, less an amount for the defects. The county court judge found for the plaintiff, awarding him the contract price minus the cost of the remedial work.
Issues
The central legal issue before the Court of Appeal was whether the contract was an ‘entire contract’ and, if so, whether the plaintiff had substantially performed his obligations under it. The court had to determine if the defects in the installation were so fundamental as to constitute a failure to perform the contract at all, thus disentitling the plaintiff to any payment, or if they were minor defects that could be rectified, allowing the plaintiff to recover the contract price less the cost of rectification. The case turned on the application and limits of the doctrine of substantial performance.
Judgment
The Court of Appeal unanimously allowed the defendant’s appeal, overturning the decision of the county court judge. It was held that the plaintiff had failed to substantially perform the contract and was therefore not entitled to recover any part of the contract price.
The Court’s Reasoning
The judgment provides a crucial analysis of the doctrine of substantial performance, distinguishing between defective performance and non-performance.
Lord Justice Sachs
Sachs LJ, giving the leading judgment, established a two-part test for determining whether performance is substantial. He emphasised that one must consider both the qualitative and quantitative aspects of the defects. He stated:
In considering whether there was substantial performance I am of opinion that it is relevant to take into account both the nature of the defects and the proportion between the cost of rectifying them and the contract price.
Applying this test, he found firstly that the ‘nature of the defects’ was severe. The central heating system failed to perform its primary function of heating the home and was, in fact, detrimental to the living conditions due to the emission of fumes. It was not merely a matter of poor workmanship but a failure to deliver the core benefit of the contract. Secondly, the proportion of the cost of rectification (£174.50) to the total contract price (£560) was significant, amounting to almost one-third. This high proportion supported the conclusion that performance was not substantial. He concluded:
It is not merely that the work was shoddy, but it is the general ineffectiveness of it for its primary purpose that leads me to that conclusion.
Lord Justice Cairns
Cairns LJ concurred, reinforcing the focus on the primary purpose of the contract. He framed the issue by asking whether the work contracted for had been ‘done’ in any meaningful sense. He contrasted this case with precedents like H. Dakin & Co Ltd v Lee, where the work was usable despite defects. Here, the system’s failure to heat the house and the presence of fumes meant the defendant had not received what he had bargained for. Cairns LJ agreed with the two factors identified by Sachs LJ:
Therefore, taking into account both the nature of the defects and the proportion which the cost of rectifying them bears to the contract price, I think that the Judge came to a wrong conclusion here and that he ought to have held that the plaintiff had not substantially performed the contract.
Implications
The decision in Bolton v Mahadeva is a landmark case in English contract law that clarifies the boundaries of the doctrine of substantial performance. It establishes that where a contractor’s work fails to meet the fundamental purpose of the contract, and the cost of remedying the defects is a significant portion of the total price, the court is likely to find a total failure of performance. This prevents a contractor from recovering any payment under an entire contract. The case serves as a critical counterpoint to Hoenig v Isaacs, demonstrating that the doctrine is not a simple-sum deduction but a holistic assessment of performance. It underscores the principle that a party cannot be forced to pay for work that is fundamentally different from, or wholly ineffective for, the purpose for which it was contracted.
Verdict: Appeal allowed. Judgment for the defendant, dismissing the plaintiff’s claim.
Source: Bolton v Mahadeva [1972] EWCA Civ 5 (13 April 1972)
Cite this work:
To cite this resource, please use the following reference:
National Case Law Archive, 'Bolton v Mahadeva [1972] EWCA Civ 5 (13 April 1972)' (LawCases.net, August 2025) <https://www.lawcases.net/cases/bolton-v-mahadeva-1972-ewca-civ-5-13-april-1972/> accessed 8 November 2025

