Frustration of contract CASES
In English law, frustration of contract occurs when an unforeseen event renders contractual obligations impossible, illegal, or radically different from the parties’ original intentions, discharging the parties from further performance.
Definition and Principles
Frustration applies where neither party is at fault, and circumstances fundamentally change the nature of the agreement. Contracts become automatically discharged from the point frustration occurs.
Common Causes
- Impossibility: Performance becomes physically or practically impossible.
- Illegality: Performance becomes unlawful due to changes in legislation or circumstances.
- Radical Change: Performance remains possible but fundamentally alters from initial expectations.
Limitations and Exceptions
- Foreseeable or self-induced events typically do not lead to frustration.
- Contracts expressly addressing certain risks (e.g., force majeure clauses) may exclude frustration.
Practical Importance
Understanding frustration ensures parties anticipate and manage risks effectively, maintaining fairness when extraordinary circumstances disrupt contractual obligations.
Home » Frustration of contract
Three local authorities jointly funded and operated a leisure complex under a 1977 agreement. Newport sought to withdraw, claiming the agreement was terminable on reasonable notice. The Court of Appeal held the agreement was not terminable without consent, as the parties intended it to last for the facility's lifetime. Facts...
Taylor agreed to hire the Surrey Gardens and Music Hall from Caldwell for four concert days. Before the first concert, the Hall was destroyed by accidental fire. The Court held that both parties were excused from performance as the contract impliedly depended on the continued existence of the Hall. This...
A tenant refused to pay rent after being expelled from leased land by Prince Rupert's hostile army during the Civil War. The court held that contractual obligations to pay rent persist despite interference by enemies, as parties must provide for such contingencies in their contracts. Facts The plaintiff (lessor) brought...
A warehouse lessee claimed frustration when street closure prevented access for 20 months of a 10-year lease. The House of Lords held that while the doctrine of frustration can in principle apply to leases, it would only do so in rare circumstances. On the facts, the interruption was insufficient to...
A contract for reservoir construction was interrupted when the Minister of Munitions ordered work to cease during WWI and dispersed the plant. The House of Lords held the contract was frustrated as the prohibition fundamentally changed conditions, making resumed performance a substantially different contract from that originally agreed. Facts The...
Charterers hired a trawler requiring a licence to operate. When only three licences were granted for their five trawlers, they chose not to license this vessel. The Privy Council held the contract was not frustrated as the appellants' own election caused the inability to perform. Facts The appellants chartered the...
A Polish company paid £1,000 in advance for textile machinery to be delivered to Gdynia. The contract was frustrated when Germany invaded Poland, making delivery impossible. The House of Lords overruled Chandler v Webster, holding that money paid for a consideration which has wholly failed is recoverable even where a...
A building contractor agreed to build 78 houses within eight months but took twenty-two months due to labour and material shortages. The contractor claimed the contract was frustrated and sought payment on a quantum meruit basis. The House of Lords held the contract was not frustrated as the work remained...
Facts The appellants (Bank Line, Ltd, “the charterers”) entered into a time charter-party with the respondents (Arthur Capel & Co, “the owners”) on 16th February 1915 for the steamship *Quito*. The charter was for a period of twelve months, commencing upon delivery of the vessel at a coal port in...